SGWS Wynwood

SGWS Wynwood Project carried out between August/November 2019 in a period of approximately 70 days. The General Direction of the Project was carried out by MJ Simpson. and consisted in the installation of different materials such as Ceramic, Porcelain, Marble, Brick Veneer and Hardwood as follows: Reception Area: 12×24″ black marble tile (1000 square feet) […]

Hard Rock Stadium (Mexican Restaurant)

The Project consisted in coating the bar counter situated at the heart of the restaurant with 8×8″ Mexican slabs that had different shades of green (700 sf), and 3×6″ travertine marble tiles on the surrounding floor (2000 sf).  Share us on:

Hard Rock Stadium (Lobby)

The General Project Management was carried out by Herman Construction and consisted on the remodeling of 72 Club and the South Gate Lobby’s floor (5,000 sf) which was done by placing tiles of 7 different sizes forming squares of 8×8 sf and then installing these pattern one next to another until covering the entire surface. […]

Therapeeds

Project carried out in September/October of 2018 from scratch, in a period of approximately 40 days that consisted in the installation of 2,500 sf of floors at a 45° angle, 3 bathrooms and 1,500 sf of relief slab walls.

Bathroom – Downtown

If you’re looking to renovate your bathroom in Edgewater, Miami, we have a team of professionals who are ready to work with you to achieve the best result. From the initial design concept to the finishing touches, we are dedicated to creating a space that meets all your needs and exceeds your expectations. With our expertise and attention to detail, you can trust us to deliver exceptional results that you will love for years to come

Balconies – Edgewater

Make the most of your balcony space with our renovation services in Edgewater, Miami. Our team of professionals will work with you to achieve the best possible result, ensuring that your balcony is not only functional but also beautiful and stylish. From new flooring and railing to custom features like built-in seating or planters, we can transform your balcony into a comfortable and inviting outdoor living space that you’ll love to spend time in.»

200 E Las Olas Boulevard

The Project was conducted under the general supervision of Mike Miller (Stiles Construction Co.) and consisted of the remodeling of the lobby floor including corridors and elevators (approximately 2000 square feet).

Kitchen – Miami

we specialize in kitchen renovation services. Our team of professionals is dedicated to helping you achieve the best possible results for your kitchen renovation project. We work closely with you to understand your needs and preferences, and provide personalized advice and recommendations to ensure that your new kitchen meets all of your expectations. With our expertise and attention to detail, we are confident in our ability to deliver exceptional results that exceed your expectations.

Griffin Pointe

The General Direction of the Project was carried out by Hernandez Construction Co. and consisted in the installation of the entire.

MJ Simpson

Project carried out between July and August 2018 in a period of approximately 40 days.